The M23 Junction 10 improvement scheme is designed to increase the capacity at Junction 10, to relieve current and future congestion.
The project is a joint venture between Persimmon Homes and Taylor Wimpey, in conjunction with National Highways and West Sussex County Council and is being undertaken as part of the Forge Wood housing development.
Breheny Civil Engineering is delivering the project which is scheduled to be completed in approximately 12 months.
The capacity improvement works comprise the following:
The works generally comprise of: site clearance, earthworks and embankment profiling, steel sheet piled retaining walls, road/pavement construction and re-surfacing, roadmarkings, signage, vehicle restraint systems, traffic signals, kerbing, gullies and drainage.
The existing noise barrier on the northbound off-slip will be taken down temporarily to permit the additional lane and retaining wall to be constructed and then re-erected in the verge once those works are completed.
There will be some disruption while the work is ongoing. To enable the construction of the additional lanes on the off slips and ‘A’ road approaches, one lane will need to be closed to ensure worker and road safety.
Some full road closures will be required, but this work will be limited to nightimes. Once confirmed, the dates and diversions will be displayed via electronic signage boards and will also be on the project website.
Updates on the works will be provided via this website and also via email to those who have registered.
If you have any questions or comments about the scheme, please feel free to contact us via email: info@m23junction10.co.uk
Click here to view the plans in the PDF format
Please register your contact details with us if you would like to be kept informed via email about the M23 Junction 10 works.
Download this month's community information leaflet which outlines progress to date on the project and what is coming up in the next month.
The next set of road closures at Junction 10 will take place during the following periods:
Night works - 12th to 14th October, 20:00 - 05:00 – The Northeast corner of the junction 10 roundabout will be closed, including the M23 southbound exit slip, the north overbridge and eastbound on Copthorne Way.
Nights works – 15th, 16th and 19th to 23rd October, 20:00 - 05:00 – The entire east side of the roundabout will be closed, including the southbound exit and entry slip, both overbridges and Copthorne Way will be closed between Copthorne Way roundabout and the M23 J10 roundabout.
A full diversion route that will be in operation can be found here
The M23 Junction 10 project is designed to increase the capacity at Junction 10 to relieve current and future congestion. These improvements have been called for by many groups and will provide significant improvement to traffic in the area once completed.
The project will support the development of new housing at the Forge Wood Development in Crawley as well as other developments in the vicinity.
No, this work will not impact vehicles using the main carriageways of the M23.
The access to the junction will be maintained throughout the project. However, one lane of the slip roads will need to be closed when being worked on to enable the construction of a third lane. Some full nighttime closures will also be required on occasions during the project, which will be advertised in advance.
Construction works are due to start during week commencing 23 February 2026.
The project is scheduled to be completed in Spring 2027.
Traffic management Lane 1 closure 24/7
Full closures of slip roads and gyratory - Occasional weekday and weekend nights only.
Standard working hours: 7.30am-6pm Monday-Friday with some weekend and night working
Yes, there will be overnight works carried out at certain times throughout the project, which will be advertised in advance.
Yes, but there aren’t any planned for the foreseeable future. Any weekend working will be notified to stakeholders in advance.
The project costs will be covered by developer contributions from Persimmon Homes and Taylor Wimpey.
Temporary lane closures will be implemented throughout the project during off peak times ensuring minimal disturbance to the traffic. Full night-time road closures will be required for certain works, but we will ensure that access is maintained for emergency services. These will be advertised in advance.
Yes, there will be a need for diversion routes whilst undertaking the night-time surfacing works. Details of the diversions will be made available in due course.
If you have a question about the M23 Junction 10 Improvement Scheme,
please contact us by emailing: